drawings do not provide actual extent of sidewalk removal and replacement for <br />the new curb ramps? <br />-Reference to JS' & 2nd paragraph of Section l 5-03M, Special <br />Instruction/Consideration. <br />D) Per special provisions section 15-03L Special Instructions/Considerations, the <br />contractor could be required to extend the flatwork removal up to 15' beyond the <br />standard curb ramp sides or extensions. If this enlargement will be determined in <br />the field by engineer during construction, how will the contractor get paid for this <br />directed change if this is considered part of the limits of work that is paid as l EA <br />handicap bid item. Are we to include 30' additional LF of removal and <br />replacement of sidewalk/curb and gutter in out estimate for these items of work <br />that could be extended without any payment adjustments? <br />-Reference to 3rd paragraph a/Section 15-0JM, Special <br />Instruction/Considerations and the last paragraph of Section 15-04, <br />E) Also, on your plan sheets A 1-1 for curb ramps on Hopyard Road at 5050 address <br />notes R/R Case "A" ADA Ramp at these locations and R/R Sidewalk call out with <br />quantity for replacement. The limits of the ADA ramp and the limits of items for <br />sidewalk replacement are not clearly identified. Please provide delineation of the <br />ADA Ramp scope that is paid under bid 1 EA line item and the sidewalk R&R <br />that is paid under SF bid item. Yous standard limits of typical curb ramp <br />replacement on G-2 includes SW areas that could be measured/included with the <br />I EA curb ramp bid item. <br />-At this location, the called-out RIR 130 SF and 40 SF S/W will be measured <br />and paid for under Remove & Replace (RIR) Sidewalk line Item . <br />F) Is the requirement to extend the removal and replacement offlatwork to the <br />nearest score mark or (E) existing 12" grove detail include the curb/gutter and AC <br />pavement area also? Can the contractor sawcut along the back of curb and replace <br />only the sidewalk section as illustrated on your typical removal detail on Dwg G- <br />2? <br />-If the new ADA ramp and wing meet ADA requirements, the curb/gutter and <br />AC pavement is not required to be removed and replaced where flatwork is <br />required to extend to the nearest score mark or existing grooves. <br />Yes , saw-cutting along the back of the curb and replacing only the sidewalk <br />section is allowed. <br />G) With Regards to adjustments of existing PG&E utilities and vaults within the <br />proposed limits of the flatwork improvements, can you please provide us with <br />contact information/persons who we can reach out to prior to bid to confirm that <br />there will be no cost to the contractor to have these items adjusted to grade during <br />the progress of the work/project. <br />nnua l urb and Gutter For St reet Resurfac ing Project <br />IP . 2 09_ Page 2 <br />DocuSign Envelope ID: DA631F0B-3C25-4585-9688-3F2684907C15