Laserfiche WebLink
Mr. Huy A. Ho, P.E. <br />The City of Pleasanton <br />January 30, 2008 <br />Page 4 <br />5.0 Preliminary Design: <br />5.1 Preliminary Data Review: Engineer will review all existing data and drawings. <br />Engineer will also conduct a site visit to review existing facilities. It is assumed <br />that City will provide necessary drawings, engineering data, and other necessary <br />information regarding existing facilities. <br />5.2 Hydraulics Study: Engineer will perform a hydraulic study, from which the results <br />will be used to confirm the required design head and capacity of the new pumps. <br />Hydraulic study will focus on the 20" PVC force main conveying wastewater from <br />the pump station to the wastewater treatment plant. Influent flows to the pump <br />station will be based on the current master plan. As part of hydraulic study, <br />available flow and pressure data from the existing pump station will be used for <br />calibration. It is assumed the City will obtain/provide this data with assistance <br />from the Engineer. <br />5.3 Project Scoping: Engineer will review and evaluate the pre-design report <br />prepared by Brian Kanga & Faulk (BKF). Recommendations on modifications to <br />the selected alternative from the report (wet well submersible pump station <br />without flowminutor) will be made to improve cost effectiveness and ability to <br />address City's needs. Recommendations will be discussed with City at <br />Preliminary Design Workshop. Decisions made at workshop will be summarized <br />in the Preliminary Design Report. <br />5.4 Design Criteria Identification: Engineer will coordinate with City to establish pump <br />station design criteria. Engineer will present draft design criteria at Project <br />Preliminary Design Workshop for discussion, comments, and finalization. <br />Outcomes of the workshop will be summarized in the Preliminary Design Report. <br />5.5 Preliminary Design Report: Engineer will prepare a Draft Preliminary Design <br />Report (PDR). Draft PDR will provide a summary of all the work completed <br />during preliminary design and be the basis for detailed design. Draft PDR will <br />include preliminary design criteria, station layouts, electrical single-line diagrams, <br />process and instrumentation diagram, project schedule, construction sequencing <br />and constraints, and cost estimate. Draft PDR will be finalized after review and <br />receipt of comments from City. <br />Deliverables: <br />• Draft and Final PDR (ten hard copies each). <br />6.0 Detailed Design: <br />6.1 Preparation of Contract Documents: ENGINEER shall prepare necessary CAD <br />drawings and technical specifications for the general, civil, architectural, <br />mechanical, structural, electrical, and instrumentation requirements to upgrade <br />Pump Station S-6. The final design will be based on the City approved PDR from <br />Task 5.0. Budget is based on no major mitigation measures being required as <br />part of the CEQA/permitting/utility coordination process, geotechnical <br />investigations, and right of way acquisition. Budget is also based on scope of <br />H:\Fnal\Pleasanton_WCO\ContracHRevisedTasklLetterHo.doc Page 4 of 6 <br />