Laserfiche WebLink
Chan - e Orders <br />A total of 38 proposed change orders were received from GradeTech, Inc. for work that <br />has been completed. These were combined into eight City change orders which are <br />grouped by similar changes, encumbering an estimated total of $213,013. Final pricing <br />has been completed on four of the eight change orders, with the other four in final <br />negotiations and awaiting supporting documentation from the contractor. A ninth change <br />order is being drafted for the proposed work for the Civic Park renovations. The <br />following details the nine change orders (see Attachment 3): <br />Storm drain system modifications <br />Extra work was performed to modify the drainage and Silva Cell system. The Silva <br />Cell system being used in this project will provide stormwater treatment for the <br />parking lot and create a larger root area below hardscaped surfaces, improving tree <br />and planting health. The storm drain lines were modified to match existing tie-in <br />conditions and site constraints. Additional aggregate base material and biotic soil <br />media were utilized to mitigate the unstable trench subgrade and to provide support <br />to the Silva Cell system under the pavement section. <br />Final cost: $29,149.83. <br />2. Modifications to the retaining wall <br />The retaining wall was adjusted to fit existing grades and required additional <br />concrete and rebar. Final cost: $2,233.46 <br />3. Electrical changes <br />The PG&E service connection point was changed by PG&E, requiring an additional <br />220 feet of trenching and conduit. Also, various minor changes with conduits, <br />lighting, wire and boxes were required for retaining wall adjustment and other site <br />constraints. Estimated cost: $21,977.25 <br />4. Planting and irrigation <br />The irrigation system within many of the planter areas was changed to bubblers to <br />improve water efficiency. The specified plantings within the parking island planters <br />were changed to provide more clearance for vehicle door swings. <br />Final Cost $21,900.41 <br />5. Additional temporary fencing <br />Additional temporary fencing was increased to encompass the area for removal of <br />the trees in Civic Park and the future park improvements. Final Cost: $2,158.62 <br />6. Various minor changes <br />Various changes were required such as adding a storm drain sleeve under the <br />retaining wall, modifying concrete curb, storm drain trench back -fill in conflict with <br />the crossing utility, modifications to paver areas, etc. Estimated Cost $1,717.90 <br />Page 4of6 <br />