Schedule <br /> The proposed schedule to complete the work on the recycled water project is as follows: <br /> August 2016 Ranger Pipelines Completes All Original Contract Work <br /> September 2016 Ken Mercer Sports Park Booster Station Design Begins <br /> September 2016 Complete Gibraltar Avenue Recycled Water Line Extension <br /> October 2016 Tassajara Reservoir Valve Vault Improvements <br /> November 2016 Project Completion <br /> Submitted :e Fiscal view: Approv d by: <br /> StepherN(irkpatrick Tina Olson N 'son Fialho <br /> Director of Engineering Director of Finance City Manager <br /> Attachments: <br /> Attachment 1: Amendment Two to RMC Agreement <br /> Page 8 of 8 <br />