<br />LESTER-SHRINER PROPERTY <br />132-8-2 <br /> Page 14 <br /> <br />6.3 REMOVAL OF EXISTING FILLS <br /> <br />While undocumented fills were not encountered in the previous explorations, artificial fills <br />(including previous test pit backfill) encountered during site grading should be over-excavated <br />and replaced as engineered fill. All fills should be completely removed from within building <br />areas and to a lateral distance of at least 5 feet beyond the building footprint or to a lateral <br />distance equal to fill depth below the perimeter footing, whichever is greater. Provided the fills <br />meet the “Material for Fill” requirements below, the fills may be reused when backfilling the <br />excavations. If materials are encountered that do not meet the requirements, such as debris, <br />wood, trash, those materials should be screened out of the remaining material and not be <br />reused. Backfill of excavations should be placed in lifts and compacted in accordance with the <br />“Compaction” section below. <br /> <br />6.4 ROCK EXCAVATION <br /> <br />Based on the previous field exploration and our experience in the vicinity, in our opinion, the <br />bedrock that underlies the site can likely be excavated with conventional construction equipment <br />such as a Caterpillar D9 bulldozer. The excavation characteristics of the bedrock will be <br />dependent on such properties as rock type, the degree of weathering, the orientations of <br />bedding planes and joints, and the strength of properties of the material. The previous <br />investigation recorded bedrock shear wave velocities during the seismic refraction survey that <br />ranged from approximately 1,300 to 8,900 feet per second. The shear wave velocities indicate <br />soft to moderate ripping is likely within the upper approximately 15 to 20 feet, while moderate to <br />hard ripping is likely below 20 feet. The prior rippability assessment presented by Lowney <br />Associates was reportedly based on information published in the Caterpillar Performance <br />Handbook. <br /> <br />It should be noted that some resistant beds of sandstone may be encountered locally that will <br />be very difficult to excavate with conventional equipment and may require the use of very heavy <br />single-tooth ripping with a Caterpillar D10, or hydraulic jacking and hammering. We recommend <br />that local grading contractors experienced in rock excavation methods be contacted to aid in <br />determining the efficiency, time and costs associated with the proposed cuts. It should be noted <br />that seismic refraction survey is considered to have an accuracy range of plus or minus 20 <br />percent. Seismic layers do not always correspond directly to lithology changes that might be <br />found in boreholes or trenching data. <br /> <br />Care should be used in estimating bedrock rippability at depths greater than 20 to 25 feet. If <br />desired, a more detailed seismic refraction survey could be performed during the design-level <br />geotechnical investigation to determine shear wave velocities at deeper depths. Since <br />additional excavation for utilities will he required in roadway areas, it may he desirable to over- <br />excavate the road subgrade and replace with compacted fill. This may reduce excavation costs <br />during storm drain, sewer, and joint trench installation. The depth of the over-excavation in <br />roadway areas would likely be on the order of 5 to 6 feet and will depend on the required utility <br />depths. Prior to over-excavating the roadway, it may be feasible to pot-hole with conventional <br />backhoe equipment once the roadway subgrade has been exposed to determine if over- <br />excavation would be appropriate. <br /> <br />Ii! CORNERSTONE <br />EARTH GROUP