Laserfiche WebLink
Hidden Canyon <br />Asphalt Paving Construction Trips Calculation <br />Paved area (sf)25,265 <br />Asphalt volume (cube feet) assume 6 inch pavement 12,632 <br />Asphalt volume (cy)468 <br />Capacity per vendor truck (CY per truck)16 <br />Trips 58.48 <br />Days in paving phase 20 <br />One-way Vendor Trips per day 6 <br />Concrete area (sf)26,136 <br />Concrete volume (cube feet) assume 4 inch thick sidewalks 8,712 <br />Concrete volume (cy)323 <br />Capacity per concrete mixer truck (CY per truck)8 <br />Trips 80.67 <br />Days in paving phase 20 <br />One-way Vendor Trips per day 8 <br />Total Trips during Paving Phase 14 <br />Appendix B 4