Laserfiche WebLink
BACKGROUND <br />On October 3, 2006, City Council awarded the contract for this project to Vanguard <br />Construction in the amount of $130,195.00. The City Council also authorized the <br />Director of Public Works to approve change orders up to the contingency amount of <br />$19,500 (15% of the contract), as it is typical that additional damaged sidewalk or curb <br />and gutter is identified during construction. During this project, a change order in the <br />amount of $13,951.47 was issued to include additional sidewalk work requested by <br />residents. <br />Submitted by: <br />/-~..,~. r. .~.. <br />Rob Wilson <br />Public Works Director <br />Fiscal Review: <br />avid P. ulver <br />Director of Finance <br />Approved b <br />Nelson Fialho <br />City Manager <br />Attachments: <br />1. Location Map <br />2. Funding and Expenditure Summary <br />Page 2 of 2 <br />