BACKGROUND <br />The subject project was authorized by the City Council as part of the 2007-08 Capital <br />Improvement Program, with an approved budget of $2,250,000. This funding includes <br />Gas Tax, General Fund, and Measure B monies. In addition to this funding, there is <br />money remaining in last year's Annual Resurfacing Project (CIP 065003) in the amount <br />of $436,152, including $367,000 programmed for reimbursement by Federal Grant <br />monies specifically tied to the resurfacing of several streets included in this current <br />project. This award of grant funds (CMATIP} was obtained through the filing of a grant <br />application that was authorized by City Council on March 7, 2006. Staff will submit the <br />final invoice to CMA for reimbursement upon project completion and execution of a <br />CMATIP funds Transfer Agreement with the CMA, which is anticipated to be executed <br />in the fall of 2007. Staff recommends the entire balance from CIP 065003, including <br />the scheduled grant money, be transferred to this project. <br />Also on the City Council agenda for July 17, 2007, is a report related to the Annual <br />Replacement of Curb and Gutters (CIP 065009) requesting approval to transfer <br />$65,000 from this project, Annual Resurfacing (CIP 075003), into the Curb and Gutter <br />project due to the discovery of adverse street conditions on Division Street. The <br />project budget located on Attachment 2 includes the transfer of the $65,000 out of the <br />resurfacing project. <br />The current project consists of approximately 1,060,000 square feet of pavement <br />resurfacing for the following streets. <br />STREET NAME BEGIN LOCATION END LOCATION AREA <br />STONERIDGE DRIVE JOHNSON DRIVE HOPYARD ROAD 348,700 <br />VALLEY AVENUE SANTA RITA ROAD E/O QUARRY LANE 179,590 <br />DIVISION STREET ST MARYS STREET ARROYO DEL VALLE 50,440 <br />ST. MARY STREET DIVISION STREET R/R CROSSING 30,955 <br />BLACK AVENUE SANTA RITA ROAD HOPYARD ROAD 173,500 <br />MOHR AVENUE MCHENRY/GATE WAY ROSEGATE WAY 36,500 <br />MCHENRY/GATE WAY MOHR AVENUE BUTTER GATE AVENUE 44,300 <br />CID WAY ALVARADO STREET KOLLN STREET 35,810 <br />NEVIS STREET SANTA RITA ROAD KOLLN STREET 36,120 <br />WELLS STREET SANTA RITA ROAD NEVIS STREET 23,976 <br />SILVER STREET SANTA RITA ROAD KOLLN STREET 40,895 <br />BONITA AVENUE ENTRADA DRIVE MIRADOR DRIVE 52,921 <br />Staff has recommended that all streets be resurfaced by the asphalt concrete overlay <br />construction method. This construction method involves grinding the edges of the <br />existing pavement, and placing a new surface course of 1.75" or 2" thickness of asphalt <br />concrete on top of the existing pavement. Black Avenue, Division Street and Saint <br />Mary Street will require a full width milling and profiling due to their existing high crown <br />condition. This method will be used in lieu of a standard wedge cut at the edge of the <br />gutter pan which will be applied on other streets. Stoneridge Drive and Valley Avenue <br />will receive a layer of Open Graded asphalt concrete, as it will provide for noise <br />reduction on these major streets. On average, material costs for open graded mix are <br />Page2of3 <br />