Phase 6: End of luly to middle of <br />September <br /> <br />Streets and sidewalks would be <br />reconstructed between St. Mary's Street and <br />the Arroyo del Valle. One half of the street <br />would be closed at a time. <br /> <br />Phase 7: End of September to the <br />end of October <br /> <br />Streets and sidewalks would be <br />reconstructed between Bernal 'Avenue and <br />West Angela Street. One half of Main <br />Street wouId be closed and southbound <br />traffic diverted to Peters Avenue. <br /> <br />· Phase 8: November 1993 <br /> <br />In this phase, clean-up, installation of street <br />t[.ees, street lighting, signs, etc. would <br />occur. 'All work should be completed by <br />Thanksgiving. <br /> <br />misc\mainst, gf <br /> <br /> <br />