4 of 14 <br />3.2 Project’s Estimated Schedule. <br />Action Plan Schedule <br /> <br />Milestone Schedule Date <br />Planned NEPA Completion Date: On or before the award date <br />Planned Draft Plan Completion Date: 15 months <br />Planned Final Plan Completion Date: 18 months <br />Planned Final Plan Adoption Date: 22 months <br />Planned SS4A Final Report Date: 24 months <br /> <br />3.3 Project’s Estimated Costs. <br /> (a) Eligible Project Costs <br />Eligible Project Costs <br />SS4A Grant Amount: $240,000 <br />Other Federal Funds: $0 <br />State Funds: $0 <br />Local Funds: $60,000 <br />In-Kind Match: $0 <br />Other Funds: $0 <br />Total Eligible Project Cost: $300,000 <br />ARTICLE 4 <br /> <br />RECIPIENT INFORMATION <br />4.1 Recipient Contact(s). <br /> <br />Cedric Novenario <br />Senior Transportation Engineer <br />City of Pleasanton <br />200 Old Bernal Avenue <br />925-931-5667 <br />cnovenario@cityofpleasantonca.gov <br />Page 33 of 218