April 2, 2024 Page 4 of 4 <br /> <br />Task Description Amendment No. 1 <br />Authorization <br />3 <br />(Modify) Final Engineering $45,000 <br />4 <br />(New) Engineering Services During Construction $65,000 <br /> Total $110,000 <br /> <br />Schedule <br />The proposed construction schedule is based on an assumed Notice to Proceed with construction on April 15, 2024, <br />with a 22-week duration for the pipeline and booster station site work construction. The installation of the pre- <br />packaged booster pump station is to be complete within 12 weeks of delivery to the site. The work under this <br />Amendment No. 1 will be completed by September 27, 2024. <br /> <br />DocuSign Envelope ID: 60B6EEC2-10BD-4EC9-B10A-6E8815C273FBDocuSign Envelope ID: 8F2AFB71-059A-494E-940A-F220B3CC700D