Approximately 90 feet of state standard-approach metal-beam guardrail was installed in <br /> the southeast quadrant of the Bernal Avenue bridge structure to improve safety. <br /> Budget <br /> The final construction cost for the project was $528,223. One change order was issued <br /> for the project for a net increase of $12,293 to cover the additional pavement repair and <br /> crack sealing that was deemed necessary in the field above the engineer's estimated <br /> quantities. <br /> Construction support services from the City's on-call consultant, Biggs Cardosa <br /> Associates (BCA), were needed during construction. BCA served as the structural <br /> review consultant (for $740) and designer for the bridge guardrail, which was authorized <br /> under the Bernal Bridge Abutment Project, CIP No. 23569. On July 18, 2023, $74,290 <br /> was transferred from the Bernal Bridge Abutment Project, CIP No. 23569, to the 2023 <br /> Streets Preventative Maintenance Project, CIP No. 23570. Staff recommends the <br /> construction support services from BCA be paid for under the subject project. <br /> Total available funding for this project was $567,987. The expenditures totaled <br /> $529,776, leaving a balance of$38,211. Staff recommends the project balance of <br /> $38,211 be returned to the Miscellaneous CIP — General Fund (Fund 201). <br /> All work and project close-out documentation has been completed to the satisfaction of <br /> the Director of Public Works. Staff recommends the City Council accept the project as <br /> complete. <br /> Submitted by: Fiscal Review: Approved by: <br /> Norm Dorais Susan Hsieh Gerry Beaudin <br /> Interim Director of Director of Finance City Manager <br /> Public Works <br /> Attachment: <br /> 1. Funding and Expenditure Summary <br /> Page 3 of 3 <br />