to be placed. The additional work is being negotiated at a reduced unit cost and
<br /> anticipated to cost $42,500. (Non-participating)
<br /> 15. PCO#15 - $5,000 For bridge 33C-0099. The bridge contractor had to replace *We
<br /> glue down delineators to temporary delineators (supplied by City) to allow paving
<br /> contractor to move traffic control devices during their work. The protective K rail
<br /> had to be temporary relocated to allow for paving and milling equipment to
<br /> perform work near the bridge. The work is being performed at Time and Material
<br /> and is estimated at $5,000.
<br /> Bridge Improvements at Various Locations, FED ID 5101 (029), CIP 16514
<br /> Participating Non
<br /> Contingency Totals Participating Local Total
<br /> Federal Share Local Share (100%Local
<br /> Project Cost
<br /> (88.53%) (11.47%) Share)
<br /> Approved Contingency(June 6,2020) $ 136,000 $ 103,322 $ 91,471 $ 11,851 $ 32,678 $ 44,529
<br /> CO#1-Phase of Construction $ 54,435 $ 54,435 $ 48,191 $ 6,244 $ 6,244
<br /> CO#2 NW Corner Conc Removal $ 7,749 $ 7,749 $ 6,860 $ 889 $ 889
<br /> CO#3 SE Add'I Flat Work $ 4,256 $ 4,256 $ 3,768 $ 488 $ 488
<br /> CO#4 SE Approach Slab Credit $ (10,000) $ (10,000) $ (8,853) $ (1,147) $ (1,147)
<br /> CO#5 Light Pole Credit* $ (3,162) $ - $ - $ (3,162) $ (3,162)
<br /> $ - $ - $ - $
<br /> Anticipated Change Orders $ - $ - $ - $ -
<br /> PCO#6 Additional Epoxy Injection $ 68,000 $ 68,000 $ 60,200 $ 7,800 $ 7,800
<br /> PCO#7 SE Corner additional Conc Removal $ 8,222 $ 8,222 $ 7,279 $ 943 $ 943
<br /> PCO#8 Extended Krail $ 12,500 $ 12,500 $ 11,066 $ 1,434 $ 1,434
<br /> PCO#9 Additional Water Line Work* $ 50,000 $ - $ - $ 50,000 $ 50,000
<br /> PCO#10 Demo Concrete SW corner @ Gas $ 5,000 $ 5,000 $ 4,427 $ 574 $ 574
<br /> PCO#11 Remove Concrete Kicker S.Flex* $ 3,000 $ - $ - $ 3,000 $ 3,000
<br /> PCO#12 Replace K-rail crash attenuator $ 6,500 $ 6,500 $ 5,754 $ 746 $ 746
<br /> PCO#13 Additional Leveling on Bridge $ 30,000 $ 30,000 $ 26,559 $ 3,441 $ 3,441
<br /> PCO#14 Extension of Paving Limits $ 42,500 $ - $ - $ 42,500 $ 42,500
<br /> PCO#15 Traffic Control Changes $ 5,000 $ - $ - $ 5,000 $ 5,000
<br /> Total CO&PCO $ 284,000 $ 186,662 $ 165,252 $ 21,410 $ 97,338 $ 118,748
<br /> Recommended Additional Contingency for
<br /> remainder of project. $ 40,000 $ 30,000 $ 26,559 $ 3,441 $ 10,000 $ 13,441
<br /> Total Anticipated Contingency $ 324,000 $ 216,662 $ 191,811 $ 24,851 ' $ 107,338 $ 132,189
<br /> Requested Contingency Increase $ 188,000 $ 113,340 $ 100,340 $ 13,000 $ 74,660 $ 87,660
<br /> *Denotes Water Line Related Work plus$5,000 of reserved contignecy(Totaling$54,838 of the$87,660)
<br /> 3