Laserfiche WebLink
filings with the State, a final project expenditure report will be presented to City Council. <br /> GSE expenditures are summarized in Attachment 1. <br /> BACKGROUND <br /> On January 16, 2018, City Council awarded the construction of the Recycled Water <br /> Infrastructure Expansion, Phase 1A — Ken Mercer Sports Park Booster Station Project, <br /> CIP No. 14126, to GSE Construction Company, Inc. for $322,800, and approved the <br /> total project budget of $381,661 . As presented to City Council, the project is largely <br /> funded through the State's Clean Water State Revolving Fund (65 percent) and <br /> Proposition 1 B grant (35 percent). The total project budget included a contingency in the <br /> amount of $33,000. The Director of Engineering was authorized to approve and execute <br /> any required contract change orders up to an amount equal to the contingency. <br /> On March 19, 2019, City Council approved a change order for GSE to construct seven <br /> debris strainers installed in the recycled water main immediately before the water <br /> meters that service Ken Mercer Sports Park and Tennis and Community Park. The <br /> additional $220,000 (change order plus contingency) of work was funded from the Parks <br /> CIP Reserve Fund 518. <br /> DISCUSSION <br /> GSE installed the prefabricated recycled water booster station and associated piping. <br /> etc. for a total of $579,618. The contractor completed the work in fall 2018, but the <br /> project was held open awaiting resolution of permanent power from PG&E. During the <br /> PG&E delay, City staff observed that the irrigation system in both Ken Mercer Sports <br /> Park and Tennis and Community Park was experiencing plugging from debris in the <br /> recycled water. Seven debris strainers were added to the project to address the <br /> plugging problems with the park irrigation systems. <br /> The project was delayed by PG&E for several reasons beyond the City's control. Due to <br /> the continued delays, the station was started and tested on generator power in <br /> December of 2018. The station has not been in service since. PG&E is now scheduled <br /> to install permanent power starting September 4, 2019. <br /> The project had seven change orders, including a final balancing change order, for a <br /> total of $256,818. This includes $206,311 for the installation of the strainers funded out <br /> of Parks CIP Reserve Fund 518. Most of the remaining change orders were associated <br /> with changes requested by PG&E, including conduit changes, increased vault sizes and <br /> meter cabinet changes. Staff recommends the transfer of the $13,689 remaining parks <br /> funds back to the Parks CIP Reserve Fund 518. <br /> GSE expenditures are summarized in Attachment 1. A total of $579,618 was expended, <br /> including $206,311 of non-eligible loan and grant work (filter strainers), leaving a total of <br /> $373,307 that can be billed to the loan and grant. The SWRCB approved Phase II of the <br /> project and is in the process of developing reimbursement paperwork for the City to <br /> invoice. There are expenditures associated with PG&E, and work performed outside of <br /> the GSE and Ranger Pipelines contracts, that the SWRCB will review to determine if the <br /> expenditures are eligible for reimbursement. Upon receipt of the final reimbursement <br /> Page 2 of 3 <br />