I. ESTIPtATED CONSTRUCTION COSTS <br /> <br />A. Street Work <br /> <br />Lump Sum: Site Clearing and <br />Grubbing, including the removal <br />of all brush, trees, fences, con- <br />crete structures, etc., within the <br />working area complete @ Three <br />Thousand, Five Hundred Thirty Doll- <br />ars ($3,530.00) <br /> <br />45,706 Sq. Ft. Finish Grading be- <br />tween property lines complete .to <br />finish subgrade complete as per <br />plan @ Four Cents ($.~04) per sq. <br />ft. <br /> <br />12,905 Cu. Yds. Rough Grading, <br />including all excavation and em- <br />bankment work complete as per grad- <br />ing plan and soils report @ Eighty- <br />two Cents ($.82) per cu. yds. <br /> <br />o <br /> <br />1,500 Cu. Yds. Remove and replace <br />all unsuitable material under filled <br />areas or in slide areas as directed <br />by the Soils Engineer complete @ <br />Seventy-eight Cents ($.78) per cu. <br />y~s. <br /> <br />7,817 Sqo Ft. 2-1/2" Asphalt Con- <br />crete Pavement, City of Pleasanton <br />Specifications, complete in place @ <br />Seventeen Cents ($.17) per sq. ft. <br /> <br />34,237 Sq. Ft. 2" Asphalt Concrete <br />Pavement, City of Pleasanton Spec- <br />ifications complete in place @ Thir- <br />teen Cents ($.13) per sq. ft. <br /> <br />42,054 Sq. Ft. 6" Aggregate Base CI.II, <br />City of Pleasanton Specifications, <br />complete in place @ Sixteen Cents <br />($.16) per sq. ft. <br /> <br />42,054 Sq. Ft. 4" Aggregate Subbase, <br />City of Pleasanton Specifications, <br />complete in place @ Ten Cents ($o10) <br />per sq. ft. <br /> <br />3,562 Sq. Ft. 4" Cushion under curb <br />and gutter, City of Pleasanton Spec- <br />ifications, complete in place @ Ten <br />Cents ($.10) per sq. fto <br /> <br />$3,530.00 <br /> <br />1,828.24 <br /> <br />10,582.10 <br /> <br />1,170.00 <br /> <br />1,328.89 <br /> <br />4,450.81 <br /> <br />6,728.64 <br /> <br />4,205.40 <br /> <br />356°2~) <br /> <br />-3- <br /> <br /> <br />