ATTACHMENT2 <br />ANNUAL SIDEWALK AND ACCESS RAMP INSTALLATION <br />CIP NO. 075005 <br />08/19/208 <br />Project Funding Amount <br />20007-08 CIP (075005) allocation -- portion approved for expenditure on <br />construction contract $86,442 <br />MTC grant $40,000 <br />Previous transfer from CIP Annual Sidewalk & Access Ramp Installation <br />(CIP 065005) $74,950 <br />Recommended additional available funding from CIP 075005 $12,150 <br />Total $213,542 <br />Project Expenditures <br />JJR Construction, Inc. Approved Construction Contract $167,827 <br />JJR Construction, Inc. Contract Change Orders (approved contingency) $33,565 <br />JJR Construction, Inc. Contract Change Orders (amount in excess of approved <br />contingency) $12,150 <br />Total Project Expenditures $213,542 <br />