During construction, when the contractor removes and replaces the access ramp or <br />sidewalk, it is anticipated that some of the adjacent sidewalk will be affected due to <br />breakage on latent or hairline cracks of the sidewalk or curb and gutter. Based on <br />previous years experience, staff is recommending a 20% project contingency <br />($41,273.12) to cover the cost of extra concrete work during construction. <br />SCHEDULE <br />The proposed schedule for the subject project is as follows: <br />Approval of Plans & Specifications and Award of Contract: May 20, 2008 <br />Start of Construction: June 2008 <br />End of Construction: July 2008 <br />Submitted by: Fiscal Review: Approve by: <br />~l <br />Rob Wilson David P. Culver Nelson Fialho <br />Public Works Director Finance Director City Manager <br />Attachments: <br />1. Bid Summary <br />2. Funding and Estimated Expenditures Summary <br />3. Contract <br />Page 3 of 3 <br />