EXHIBIT "B" <br /> PRELIMINARY SCHEDULE <br /> <br /> 1. Review existing reports and plans, February 1 - February 28, 1986 <br /> cost estimates and rules <br /> <br />2. Prepare Project Summary of Cost March 1 - March 20, 1986 <br /> and Preliminary Engineer's Report, <br /> Assessment Diagram, Boundary Map <br /> and Description of Work <br /> <br />3. Petition to be circulated to owners February 20 - March 20, 1986 <br /> for 60% sign up <br /> <br />4. Meeting with property owners to April 10, 1986 <br /> review draft report and project <br /> <br />5. Prepare final draft Engineer's May 6, 1986 <br /> Report and submit to Council for <br /> approval, with approval to advertise <br /> work for construction <br /> <br />6. Receive bids June 6, 1986 <br />7. Respread per low bid June 10, 1986 <br />8. Public Hearing June 17, 1986 <br />9. Bonds sold July 22, 1986 <br />10. Notice to Proceed August 5, 1986 <br /> <br /> <br />