ATTACHMENT 6 <br />Gingerbread Play Yard Project <br />Projected Timeline <br />Master Plan Development <br />Design Review/Approval <br />Parks and Recreation Commission <br />Construction Documents/Cost Estimate Development <br />Funding Approval City Council <br />100% Complete <br />City Council <br />Bid Process <br />Open <br />Closed <br />Award of Contract <br />Building Packed <br />Construction Start <br />Construction Complete <br />City Council <br />Move In <br />Maintenance Period Complete <br />Project Accepted <br />City Council <br />December 6, 2007 <br />January 15, 2008 <br />April 11, 2008 <br />(3 months) <br />April 15, 2008 <br />April 18, 2008 <br />May 9, 2008 <br />(3 weeks) <br />May 20, 2008 <br />May 27-30, 2008 <br />June 2, 2008* <br />September 12, 2008* <br />(3 1/2 months) <br />September 15-26, 2008 <br />December 26, 2008 <br />(90 days) <br />January 20, 2009 <br />*These dates may change as the Master Plan/Construction Documents are completed and construction <br />begins. <br />