ACTIA Bicycle/Pedestrian Countywide Discretionary Fund Program ACTIA No. A07-0014 <br />Cycle 3 Grant Funding Agreement Attachment B (cont.) <br />Project Milestone Schedule: Table B-2 below shows a milestone schedule for the Project. <br />Table B-2: Project Milestone Schedule <br />Project Milestone Date <br />ACTIA Grant Awarded March 22, 2007 <br />Grant Notice to Proceed July 1, 2007 <br />Begin Environmental Studies February 2006 <br />Complete Feasibility Study November 2006 <br />Environmental Approval (CEQA) December 2006 <br />Environmental Approval (NEPA) NA <br />Begin Detailed Design (PS&E) October 31, 2007 <br />Complete Detailed Design (Final PS&E) September 30, 2008 <br />Submit Final Invoice/Project Closeout December 31, 2008 <br />Grant Funding Period Complete June 30, 2009 <br />Grant Funding Agreement Expires October 31, 2009 <br />BikePed-Cycle3-A070014-EBRPD-AlamoCanalTrail Page 12 of 19 <br />