status to the Contractor every week. The status <br />schedule serves a number of functions: <br />• It lets the Contractor know that we are <br />serious about the schedule. The Contractor <br />will take the schedule more seriously if he <br />believes that liquidated damages may be <br />aggressively pursued. <br />• It reduces conflicts about additional days. <br />Since each update provides the number of <br />days for the week charged to the contract <br />and the total number of days to -date charged <br />to the contract, differences of opinion about <br />contract days are resolved quickly. When <br />the differences are resolved quickly, the <br />resolution tends to be fairer to both parties. <br />• It induces a sense of urgency in the <br />Contractor since he sees every week how <br />many days are left before liquidated <br />damages can be assessed. A sense of <br />urgency is also induced because the <br />Contractor will not feel like he can argue for <br />more time at the end of the project. <br />Tetra Tech's Construction Manager will review <br />the construction schedule with the City's Project <br />Manager and Design Engineer for acceptability <br />on monthly basis. <br />Testing and Record Drawings <br />Through our experience on similar projects, we <br />have learned that final testing and closeout items <br />typically delay project completion. To reduce <br />these delays, we will obtain sign -offs from <br />permit agencies as soon as applicable when <br />portions of the work are completed. We will also <br />review the Contractor's record drawings each <br />pay period to verify that the drawings are kept <br />up to date. <br />Surveying, Geotechnical Engineering <br />and Laboratory Testing <br />It is Tetra Tech understands that the City will <br />engage other consultants to provide the <br />necessary construction material and geotechnical <br />testing, survey staking, and specialty <br />inspections. Our Construction Manager will <br />City of Pleasanton - Project No. 991 035 <br />Exhibit A <br />contact representatives of these consultants to <br />effectively coordinate and schedule the activities <br />with the construction contractor and City's <br />Project Manager. <br />Project Close -Out <br />Tetra Tech will coordinate with City staff, <br />design consultant, and contractor to prepare <br />project close -out items, such as the following: <br />• Warranty work prior to contractor's <br />demobilization. <br />• Final inspections and deficiency reports. <br />• Lien waivers, bonds, guarantees, and <br />warranties, as applicable. <br />• Certificates of acceptance and substantial <br />completion. <br />The Tetra Tech Team will finalize and submit <br />contract records and documents, including final <br />record drawings, and a report to summarize <br />performance of the contracts, contract changes, <br />and final resolution of significant contract issues. <br />Coordination with City Staff <br />Tetra Tech will provide overall project <br />management of the project. Our Construction <br />Manager will report to and take direction from <br />the Project Manager assigned by the City's <br />Public Works Department. The Department may <br />assign other duties, not defined above, that are <br />related to the project. The Contractor will make <br />available a Class "A" construction trailer for use <br />by our Construction Manager and inspector. <br />Tetra Tech's construction management team are <br />equipped with cellular phones to ensure <br />accessibility and facilitate immediate <br />communications with the City. Communications <br />will be further enhanced via land -line telephone <br />service, fax and/or e-mail. This will ensure that <br />the City's Project Manager will be kept informed <br />with up -to -the- minute information. <br />TETRA TECH INC. <br />1 -7 <br />