My WebLink
|
Help
|
About
|
Sign Out
12
City of Pleasanton
>
CITY CLERK
>
AGENDA PACKETS
>
2021
>
120721
>
12
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
12/1/2021 4:15:11 PM
Creation date
12/1/2021 4:14:18 PM
Metadata
Fields
Template:
CITY CLERK
CITY CLERK - TYPE
AGENDA REPORT
DOCUMENT DATE
12/7/2021
DESTRUCT DATE
15Y
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
104
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
<br /> NOVEMBER 2021 | 15 <br />Task 11.2 – Feasibility Review of Alternative Well Locations TM <br />Carollo will develop a TM to summarize the feasibility of siting two Wells at Alisal Elementary School. The TM <br />will consider siting constraints, operations considerations, pipelines, public/school impacts, schedule/cost <br />impacts etc. to evaluate the feasibility of these locations. LSCE will provide input on potential well sites <br />related to hydrogeology, water quality, and well production based on a desktop study. <br />Task 11.3 – Property Acquisition and/or Temporary Construction Easement Allowance <br />It is anticipated temporary construction easements at the Alisal Elementary school will be needed to <br />construct Well 10. Associated Right of Way will provide property acquisition services. This task includes an <br />allowance of $25,000. Carollo will submit a scope and cost estimate after the required easements are further <br />defined for the City’s approval prior to beginning work. <br />Task 11 Deliverables: <br />· Feasibility review of alternative well locations TM. <br />Task 11 Assumptions: <br />· The following items are not included in the feasibility review for alternative well locations. <br />- Test drilling <br />- Ground survey <br />- Geotechnical investigations <br />Optional Task 12 – Not Used <br /> <br />Optional Task 13 – Additional Well 8 Investigations and Rehabilitation Services <br />Task 13.1 – Well 8 Flow Profiling and Depth Discrete Sampling <br />LSCE will lead the Well 8 Flow Profiling and Depth Discrete Sampling. The Well 8 Flow Profiling and Depth <br />Discrete Sampling is in Attachment E Task 13.1. <br />Task 13.2 – Well 8 Rehabilitation Allowance <br />LSCE will lead the Well 8 Rehabilitation. This task includes an allowance of $250,000. The Well 8 <br />Rehabilitation scope of work is included in Attachment E Task 13.2. <br />Key Staff <br />The following lists the Consultants key staff and their roles in the design of the Project. <br />· Principal-in-Charge – Tom Gillogly <br />· Project Manager – Darren Baune <br />· Design Manager – Brad Jeppson <br />· DWSRF loan Application – Seema Chavan <br />The following list key subconsultants and their roles in the design of the Project. <br />· Electrical design – Pezzoni Engineering, Inc.
The URL can be used to link to this page
Your browser does not support the video tag.