Staff recommends City Council award the construction contract base bid plus bid <br /> additive to the lowest and responsive bidder Ashron Construction and Restoration, Inc. <br /> for $519,120. <br /> Schedule <br /> The proposed schedule for the project is as follows: <br /> Approval of Plans and Specifications/Award of Contract September 7, 2021 <br /> Contractor to Start Construction October 2021 <br /> Construction Complete February 2022 <br /> The fire training tower will remain closed throughout implementation of the project. <br /> Submitted by: Fiscal Review: Approved by: <br /> / del/s1 )1143— /A/L.- /a/ <br /> Adam Nelkie Tina Olson Nelson Fialho <br /> Acting Director of Engineering Director of Finance City Manager <br /> Attachments: <br /> 1. Funding and Estimated Expenditures Summary <br /> 2. Photo Log <br /> 3. Bid Summary <br /> Page 5of5 <br />