Laserfiche WebLink
All other components of the SMC bid were found to be responsive to the bid solicitation, <br /> and references for SMC were also verified. Staff recommends awarding the Pioneer <br /> Cemetery Entry and Wayfinding Improvements Project to Suarez & Munoz <br /> Construction, Inc. in the amount of $394,240. <br /> Schedule <br /> The proposed schedule for this project is as follows: <br /> Approval of Plans and Specifications and Award of Contract August 20, 2019 <br /> Estimated Start of Construction September 2019 <br /> Estimated End of Construction November 2019 <br /> Submitted by: - Reviewed by: Approve by: <br /> Stephen Kirkpatrick Tina Olson Nelson Fialho <br /> Director of Engineering Director of Finance City Manager <br /> Attachments: <br /> 1. Bid Summary <br /> 2. Protest Letter from Marina Landscape, Inc. <br /> 3. Estimated Funding and Expenditure Summary. <br /> Page 3 of 3 <br />