Bid Result for: Dolores Bengtson Aquatic Center Locker Room Renovation,CIP 17706 ATTACHMENT NO.2
<br /> May 2,2018
<br /> Dolores Bengtson Aquatic Center Locker Room Renovation
<br /> Owner:City of Pleasanton
<br /> Bid Opening:05/02/18 •marks an allowance Engineer's Estimate Saboo Inc Integra Construction Services ICC General Contractors,Inc
<br /> 1606 MONTCLAIR PL 4133 Mohr Avenue,Suite D 510 S.Mathilda Avenue,Suite
<br /> BRENTWOOD, CA 94513 Pleasanton, CA 94566 Sunnyvale, CA 94086
<br /> Bidder Status:Valid Bidder Status:Valid Bidder Status:Valid
<br /> Bid Items
<br /> Item# Item Code Item Description rantity Unit of Measure Unit Price Item Total Unit Price Item Total Unit Price Item Total Unit Price Item Total
<br /> 1 DBAC LOCKER ROOM RENOVATION 1 LS $1,555,000.00 $1,555,000.00 $1,930,000.00 $1,930,000.00 $2,078,650.00 $2,078,650.00 52,132,357.00 $2,132,357.00
<br /> ADD ALT 1:ONE ADDITIONAL
<br /> TEMPORARY TRAILER SHOWER(8
<br /> SHOWERS)ON A MONTHLY BASIS
<br /> INCLUDING ALL OF THE WORK
<br /> 2 NECESSARY PER SECTION 01500 6 EA $7,500.00 $45,000.00 $10,000.00 $60,000.00 $7,725.00 $46,350.00 $6,875.00 $41,250.00
<br /> Engineer's
<br /> Bid List Total Estimate $1,600,000.00 $1,990,000.00 $2,125,000.00 $2,173,607.00
<br /> Total Bid Amount $0.00 $1,990,000.00 $2,125,000.00 $2,173,607.00
<br /> Listed Subs
<br /> I •marks an allowance Engineer's Estimate CWS Construction Group,Inc. Southwest Construction& Rodan Builders
<br /> 94 San Benito Way,Novato,CA, 1213 San Mateo Avenue 859 Cowan Road
<br /> San Bruno, CA 94066 Burlingame, CA 94010
<br /> US
<br /> Bidder Status:Valid Bidder Status:Valid Bidder Status:Valid
<br /> Bid Items
<br /> Item# Item Code Item Description entity Unit of Measure Unit Price Item Total Unit Price Item Total Unit Price Item Total Unit Price Item Total
<br /> 1 DBAC LOCKER ROOM RENOVATION 1 LS $1,555,000.00 $1,555,000.00 $2,168,000.00 $2,168,000.00 $2,719,945.00 $2,719,945.00 $2,870,000.00 $2,870,000.00
<br /> ADD ALT 1:ONE ADDITIONAL
<br /> TEMPORARY TRAILER SHOWER(8
<br /> SHOWERS)ON A MONTHLY BASIS
<br /> INCLUDING ALL OF THE WORK
<br /> 2 NECESSARY PER SECTION 01500 6 EA $7,500.00 $45,000.00 $15,000.00 $90,000.00 $7,000.00 $42,000.00 $12,229.00 $73,372.00
<br /> Engineer's
<br /> Bid List Total Estimate $1,600,000.00 $2,258,000.00 $2,761,945.00
<br /> Total Bid Amount $0.00 $2,258,000.00 $2,761,945.00
<br /> Listed Subs
<br /> _There was an extension error for Rodan Builders of$2.00; This error did not affect the ranking of the bidders.