Laserfiche WebLink
The final construction contract cost including contract change orders was $2,680,625. <br /> The following change orders resulted in a net increase of $128,629 to the contract <br /> amount: <br /> • Increase of $29,500 for roadway repair on Hopyard Road. Uneven pavement <br /> surface/vertical separation at the bridge approach on the southwest section at <br /> Hopyard Road and Arroyo Mocho created unfavorable conditions for vehicular <br /> traffic. <br /> • Increase of$31,000 for paving of 6,240 square feet of existing dirt drive-thru plus <br /> placement of ground recycled asphalt concrete material on 6,000 square feet of <br /> existing dirt parking lot. This was a temporary dust control measure on the <br /> temporary downtown parking lot located next to Delucchi Park between Neal Street <br /> and Angela Street. <br /> • Increase of $76,120 for roadway repair at 21 locations along West Las Positas <br /> Boulevard between DMV and Stoneridge Drive. The repair was not included under <br /> the original construction contract, however excessive roadway sinking at these <br /> locations warranted the immediate repair to provide a safe driving condition for <br /> motorists. More than 20,000 square feet of existing depressed pavement was <br /> milled and leveled with 1/2-inch hot mix asphalt concrete. 1,200 square feet of <br /> distressed pavement was also repaired. <br /> • Increase of $34,300 for work performed on existing City-owned vacant parcel on <br /> south side of St. Mary/Division Street immediately east of the railroad crossing. <br /> Work included clearing, grading, installation of a new concrete driveway entrance <br /> on St. Mary Street, and installation of a new 2-1/2 inch layer of recycled/ground <br /> asphalt concrete material on the existing dirt surface to provide 45 additional <br /> temporary parking stalls for high demand downtown parking. <br /> • Decrease of$42,290.62 as the result of a decrease in contract line item quantities, <br /> such as asphalt concrete, leveling, and paving fabric as compared to the <br /> engineer's estimate of quantities (balancing change order). <br /> Alameda County Transportation Commission (Alameda CTC) has implemented the Time <br /> of Use policy for Measure B funding and VRF funding. In order not to jeopardize this <br /> funding, we must use a specified amount of each type within the fiscal year. As we are <br /> approaching the end of the fiscal year, we have not yet expended the required amount of <br /> either Measure B or VRF funds. Staff is recommending that Measure B and VRF funding <br /> be used for the Annual Resurfacing and Preventative Maintenance project, CIP No. <br /> 145003, which is now complete. Gas Tax and Streets CIP funds, both of which do not <br /> have restrictions on the time of use, will be switched out with Measure B and VRF funds <br /> from the upcoming Annual Resurfacing project, CIP 155003. Total funding for each <br /> project will remain the same as Council previously authorized, but funding sources will be <br /> switched. Each of these projects is eligible to use both Gas Tax and Streets CIP funding. <br /> The final project funding and expenditures are summarized in Attachment 1 to this report, <br /> indicating total project expenses of $2,680,625. The budget for the project was reduced <br /> by $30,000 as a result of the Finance Department balancing the previous year's project <br /> Page 5 of 6 <br />