TRADE ONLY PERMIT-ELECTRICAL FEES WORKSHEET
<br /> ITEM UNIT PRICE
<br /> Electrical Permit Issuance Fee $23.50
<br /> New Single-Family Dwelling Electrical Permit Fee 50.056 per square foot
<br /> New Multi-Family Dwelling Electrical Permit Fee 50.050 per square foot
<br /> Electrical Plan Review Fee 25%of Electrical Permit fee,minimum one-hour,
<br /> 5130.00
<br /> Additional Plan Review(more than one initial recheck, Minimum one-hour,$130.00,or based upon review
<br /> or for revisions to previously approved plans) time multiplied by the current reviewer rate,plus a
<br /> $20.00 admin fee
<br /> Appliances 54.75 each
<br /> Busways S7.25 per 100 lineal feet
<br /> General Circuits $5.25 per circuit
<br /> Generators(under 10 kVA) $23.50 each
<br /> Lighting Fixtures
<br /> First 20 fixtures $1.10 each
<br /> Fixtures exceeding 20 $0.73 each
<br /> Miscellaneous Electrical Apparatus $18.20 each
<br /> Motors or Generators
<br /> Up to 1 HP (s 1 kVA) $4.75 each
<br /> Up to 10 HP (<_10 kVA) $12.30 each
<br /> Up to 50 HP (<_ 50 kVA) $24.60 each
<br /> Up to 100 HP (s 100 kVA) $49.50 each
<br /> Over 100 HP (>100 kVA) $74.50 each
<br /> Photo-Voltaic Systems,Residential
<br /> Up to 15kW $150.00, plus one-hour plan review fee
<br /> Over 15kW $370.00, plus$15 per additional kW above 15,and
<br /> one-hour plan review fee
<br /> Photo-Voltaic Systems,Non-Residential
<br /> Up to 50kW 5240 min,S16 per kW,plus two-hour plan review fee
<br /> Over 50kW $12 per kW,plus$5 per additional kW above 50,and
<br /> four-hour plan review fee
<br /> Receptacles,Switches,Other Outlets
<br /> First 20 outlets $1.10 each
<br /> Outlets exceeding 20 $0.73 each
<br /> Electrical panels
<br /> Up to 199 amp (under 600 volts) $30.50 each
<br /> Up to 999 amp(under 600 volts) $62.15 each
<br /> 1000 amp or more(under 600 volts) $124.30 each
<br /> All panelboards over 600 volts 5124.30 each
<br /> Signs,marquees $24.60 each
<br /> Private Spa or Swimming Pool $49.50 each
<br /> Temporary Power(Pole or Pedestal) S23.50 each
<br /> Temporary Power Distribution(for construction sites, 512.30 each
<br /> seasonal lots,etc.,per pole or pedestal)
<br /> Transformers $66.50 each
<br /> REVISED:Mar 16 2015;Jan 1,2015,Jul 1 2014;Apnl 1,2014;Jan.1,2014;Oct 31,2013;Jul 1,2013,March 1,2013;Jan 1,2013'
<br /> July f+P July
<br /> March 1,2012;Jan.1,2012;Oct.6,2011;July 1,2011;March 1,2011;Jan.1.2011:Nov 15,2010;Aug.1,2010.July 1,2010;Feb 24,
<br /> 2010,Jan 1,2009;Oct.30.2008:July 1.2008,Jan.1.2008;Dec 10,2007;Jan 3,2007;Jan 1,2007,Dec 1,2006;Nov 13.2006;July
<br /> 14,2006;Jan 3,2006;July 14,2005;Nov 7,2004,July 2,2004; May 10,2004;March 3,2003;Jan 31,3004;Apnl 12,2002,March 15,
<br /> 2002,Sept 6,2001,Jan 5,2001
<br /> Page 10 of 10
<br /> Fees Handout as of 03-16-15
<br /> 11
<br />
|