ELECTRICAL PERMIT FEE WORKSHEET
<br /> ITEM UNIT PRICE
<br /> Electrical Permit Issuance Fee $23.50
<br /> New Single-Family Dwelling Electrical Permit Fee $0.056 per square foot
<br /> New Multi-Family Electrical Permit Fee $0.050 per square foot
<br /> Electrical Plan Review Fee 25% of Electrical Permit fee, minimum one-hour,
<br /> $130.00
<br /> Additional Plan Review (more than one initial recheck, Minimum one-hour, $130.00, or based upon review
<br /> or for revisions to previously approved plans) time multiplied by the current reviewer rate, plus a
<br /> $20.00 admin fee
<br /> Appliances $4.75 each
<br /> Busways $7.25 per 100 lineal feet
<br /> General Circuits $5.25 per circuit
<br /> Generators (under 10 kVA) $23.50 each
<br /> Lighting Fixtures
<br /> First 20 fixtures $1.10 each
<br /> Fixtures exceeding 20 $0.73 each
<br /> Miscellaneous Electrical Apparatus $18.20 each
<br /> Motors or Generators
<br /> Up to 1 HP (<_ 1 kVA) $4.75 each
<br /> Up to 10 HP (5 10 kVA) $12.30 each
<br /> Up to 50 HP (5 50 kVA) $24.60 each
<br /> Up to 100 HP (5 100 kVA) $49.50 each
<br /> Over 100 HP (> 100 kVA) $74.50 each
<br /> Photo-Voltaic Systems, Residential
<br /> Up to 15kW $150.00, plus one-hour plan review fee
<br /> Over 15kW $370.00, plus $15 per additional kW above 15, and
<br /> one-hour plan review fee
<br /> Photo-Voltaic Systems, Non-Residential
<br /> Up to 50kW $240 min, $16 per kW, plus two-hour plan review fee
<br /> Over 50kW $12 per kW, plus $5 per additional kW above 50, and
<br /> four-hour plan review fee
<br /> Receptacles, Switches, Other Outlets
<br /> First 20 outlets $1.10 each
<br /> Outlets exceeding 20 $0.73 each
<br /> Electrical panels
<br /> Up to 199 amp (under 600 volts) $30.50 each
<br /> Up to 999 amp (under 600 volts) $62.15 each
<br /> 1000 amp or more (under 600 volts) $124.30 each
<br /> All panelboards over 600 volts $124.30 each
<br /> Signs, marquees $24.60 each
<br /> Private Spa or Swimming Pool $49.50 each
<br /> Temporary Power (Pole or Pedestal) $23.50 each
<br /> Temporary Power Distribution (for construction sites, $12.30 each
<br /> seasonal lots, etc., per pole or pedestal)
<br /> Transformers $66.50 each
<br /> REVISED:April 1,2014;Jan. 1,2014;Oct.31,2013;July 1,2013;March 1,2013;Jan. 1,2013: March 1,2012;Jan. 1,2012;Oct.6,2011;
<br /> July 1, 2011; March 1,2011;Jan. 1,2011; Nov. 15,2010;Aug. 1,2010; July 1,2010; Feb.24,2010;Jan. 1, 2009; Oct. 30,2008; July 1,
<br /> 2008; Jan. 1,2008; Dec. 10,2007; Jan. 3, 2007; Jan. 1, 2007; Dec. 1, 2006; Nov. 13, 2006; July 14, 2006; Jan. 3, 2006; July 14, 2005;
<br /> Nov. 7,2004;July 2,2004; May 10,2004;March 3,2003;Jan. 31,3004;April 12,2002,March 15,2002,Sept.6,2001,Jan.5,2001.
<br /> Page 10 of 10
<br /> Fees Handout as of 04-01-14